See how far we've come.

Project Archives

Construction Alert: Week of April 21, 2025

Striping continues the week of April 21; bus pad construction is scheduled for late April and early May COMPLETED: Paving on SR111 in the project area
Read More

Construction Alert: Week of April 14, 2025

Final nights of repaving on SR 111 roadway project. Work to continue in late April with bus pad and cross-gutter construction. Nighttime paving operations are nearing completion. Crews will continue night work on Tuesday, April 15, and Wednesday, April 16, as the last section of the project area is repaved. Work will continue in late…
Read More

Construction Update: April 3, 2025

SR 111 Nighttime Repaving Will Continue In Mid-April for 2 to 3 nights. Concrete bus pads to begin construction in May.
Read More

Construction Alert: Week of March 24, 2025

Ongoing Nighttime Repaving and Lane Closures Continue on N. Palm Canyon Drive and Vista Chino. Please see full alert below.
Read More

Construction Update: March 19, 2025

Schedule Update: Work locations have changed for Wednesday, March 19, and Thursday, March 20. Please see the revised maps via the alert below.
Read More

Construction Alert: Week of March 17, 2025

Nighttime roadwork continues throughout project area; please watch for No Parking signs on Vista Chino and N. Palm Canyon Drive.
Read More

Construction Update: March 13, 2025

Tonight’s nighttime work on Thursday, March 13, is postponed due to weather. Crews will resume work on Monday, March 17, weather permitting. Check back here for schedule updates. Thank you for your patience as we continue improving SR111. Drive safely!
Read More

Construction Alert: Week of March 10

Nighttime roadwork continues throughout the project area. View the latest construction alert below.
Read More

Construction Alert: Week of March 3

Night work scheduled to reduce traffic delays on SR 111 Roadway Project In response to public concerns about traffic congestion and delays, the construction team along with the City of PalmSprings collaborated to make an exception to City policy and change construction to nightwork. Nightwork is scheduled Monday through Thursday nights from 7 p.m. to…
Read More

Construction Update: Week of February 24

No roadwork is planned for the SR111 Roadway Project through Friday, Feb. 28. Please check back on Thurs., Feb. 27 for an updated schedule.
Read More

Construction Alert: Monday, February 24

Lane Closures to Continue on Gene Autry Trail—USE ALTERNATE ROUTESOngoing construction activity with lane closures is planned as crews continue repaving work along key sections of Gene Autry Trail. These improvements are part of the SR111 Roadway Project, a broader effort to enhance road safety, improve driving conditions, and extend the lifespan of the roadway.
Read More

Construction Update: Week of February 17

Repaving work continues on Gene Autry Trail beginning February 19, with construction starting at the intersection of Ramon Road and Gene Autry Trail, extending north to Vista Chino. Once the northbound work is complete at Vista Chino, construction crews will close the southbound inside lane on Gene Autry Trail and repave to Ramon Road.
Read More