Construction Alert: Week of April 21, 2025
Striping continues the week of April 21; bus pad construction is scheduled for late April and early May COMPLETED: Paving on SR111 in the project area
Read MoreConstruction Alert: Week of April 14, 2025
Final nights of repaving on SR 111 roadway project. Work to continue in late April with bus pad and cross-gutter construction. Nighttime paving operations are nearing completion. Crews will continue night work on Tuesday, April 15, and Wednesday, April 16, as the last section of the project area is repaved. Work will continue in late…
Read MoreConstruction Update: April 3, 2025
SR 111 Nighttime Repaving Will Continue In Mid-April for 2 to 3 nights. Concrete bus pads to begin construction in May.
Read MoreConstruction Alert: Week of March 24, 2025
Ongoing Nighttime Repaving and Lane Closures Continue on N. Palm Canyon Drive and Vista Chino. Please see full alert below.
Read MoreConstruction Update: March 19, 2025
Schedule Update: Work locations have changed for Wednesday, March 19, and Thursday, March 20. Please see the revised maps via the alert below.
Read MoreConstruction Alert: Week of March 17, 2025
Nighttime roadwork continues throughout project area; please watch for No Parking signs on Vista Chino and N. Palm Canyon Drive.
Read MoreConstruction Update: March 13, 2025
Tonight’s nighttime work on Thursday, March 13, is postponed due to weather. Crews will resume work on Monday, March 17, weather permitting. Check back here for schedule updates. Thank you for your patience as we continue improving SR111. Drive safely!
Read MoreConstruction Alert: Week of March 10
Nighttime roadwork continues throughout the project area. View the latest construction alert below.
Read MoreConstruction Alert: Week of March 3
Night work scheduled to reduce traffic delays on SR 111 Roadway Project In response to public concerns about traffic congestion and delays, the construction team along with the City of PalmSprings collaborated to make an exception to City policy and change construction to nightwork. Nightwork is scheduled Monday through Thursday nights from 7 p.m. to…
Read MoreConstruction Update: Week of February 24
No roadwork is planned for the SR111 Roadway Project through Friday, Feb. 28. Please check back on Thurs., Feb. 27 for an updated schedule.